Building Safety Levy (effect from 1 October 2026) 

 

The Building Safety Levy (England) Regulations 2025 were made on 19 November 2025 as part of the Goverment's approach to help fund costs associated with remediating building safety defects across England.

From 1 October 2026, developers submitting certain building control applications and initial notices will need to consider the Building Safety Levy.   Building control full plans applications / initial notices / high rise building (HRB) applications for works providing at least 1 dwelling or a bedspace in Purpose Built Student Accommodation will have to provide information on a separate form for the purposes of the levy, otherwise the application may be rejected (or in the case of initial notices, Building Control must reject the initial notice if the levy information has not been included).

 

Which type of development does this apply to?

  • at least 10 new dwellings; or
  • at least 30 new bedspaces in purpose-built student accommodation.

Mixed-use developments and conversions may also be liable where they create sufficient new residential accommodation. 

 

Building Safety Levy Charging Form  (Word version)

 Building Safety Levy Charging Form  (pdf version)

 

Developers will need to submit the completed form with the relevant application form to Building Control at Oldham Council. 

 

Exemptions

Small developments with fewer than ten units are exempt from the levy charge. Other types of building that are exempt include:

  • affordable and supported housing
  • housing developed by non-profit registered providers and their wholly owned subsidiaries
  • care homes and hospices
  • hospitals and certain NHS accommodation
  • hotels and hostels
  • school accommodation
  • certain temporary accommodation for homeless people

Developers should check the regulations and government guidance carefully before assuming that an exemption applies. 

The Building Safety Levy (England) Regulations 2025

 

How is the levy calculated?

 The levy is calculated based on the amount of residential floorspace and is measured in square metres.  Rates are published in the rates table Building Safety Levy Guidance 

 Rates will vary by local authority and whether the development is on previously developed land (which attracts a 50% discount).  To qualify, at least 75% of the land within the relevant planning permission boundary must, in general, meet the levy definition of previously developed land.

 

Payments and Completion Certificates  


 Payment must be made to Oldham Council Building Control prior to the earlier of:

  • occupation of the development, or
  • completion of the building work

If the developer fails to pay the levy we will withhold the completion certificate or reject the final certificate.

 

Reviews and Appeals

If a developer disagrees with a levy charge, a refund amount or decision not to issue a refund, they can request a review.  A review must be requested from Oldham Council Building Control within 28 days.

If a developer remains in dispute they can appeal the matter to the First Tier Tribunal.