We’re prioritising improvements to the borough’s roads as part of our major £12m Highways Improvement Programme 2019/20 – 2021/22.

The approved 3-year programme of works is designed to ensure the surfaces of our streets, roads and cul-de-sacs are high quality, durable and safe - supporting residents and motorists.

Specialist teams will be out across Oldham making sure hundreds of kilometres of carriageway are fit for purpose and brought up to standard.

Estimated Delivery dates are subject to change due to weather conditions and other factors.
 
Information on the first year of the programme (2019/20) will be updated on a regular basis as schemes are progressed and delivery dates confirmed.

2019/20 programme

Ref Scheme Name Extents  Ward  Est. Delivery Date Description of Scheme Status
1 A672 Ripponden Road Dumfries Ave to Boundary Saddleworth North September / October Pre Patching  
2 C19454 Stannybrook Road Daisy Nook Farm to Boundary Failsworth East September / October Resurface  
3 Greenacres Road Top St to Dunham St Waterhead August Resurface  
4 Higginshaw Lane Higginshaw Rd to Rudding St Royton South August Resurface  
5 Dowry Street Full Length Medlock Vale October Resurface  
6 Mill Gate / Colenso St Full Length Hollinwood May Resurface Completed
7 Roundthorn Road Cranberry Rd to Brewerton Rd St. Mary's July Resurface Completed
8 Ellen Street Full Length Coldhurst July Resurface Completed
9 Falcon Street Full Length Alexandra October Resurface Completed
10 Leefields Close Full Length Saddleworth South July Resurface Completed
11 Wharmton Rise Full Length Saddleworth South June Resurface  
12 Beresford St Full Length Failsworth West September Resurface  
13 Hollins Avenue Full length Saddleworth West and Lees July Resurface  
14 Fitton Hill Road Full Length Alexandra October Resurface  
15 Coniston Avenue Full Length Werneth June Resurface Completed
16 Levington Drive Full Length Medlock Vale November Resurface  
17 Longfield Park Full Length Crompton August Resurface Completed
18 Blakelock Street Full Length Crompton August Resurface Completed
19 Houson Street Full Length Alexandra October Resurface  
20 Higher Arthurs Full Length Saddleworth South August Resurface  
21 Chapel St / Pearson Gr Full Length Saddleworth West and Lees June Resurface  
22 Orchard Road Full Length Failsworth East September Resurface Completed
23 Goldsmith Avenue Full Length St. James' August Resurface  
24 Back Lane Junction with Thorpe Lane Saddleworth North July Resurface  
25 Sunfield Lane Dorset Avenue to End Saddleworth North October Resurface  
26 Whitehead Street Full Length Crompton September Resurface  
27 Ashmond Road Full length Saddleworth West and Lees November Resurface  
28 Cosgrove Road Full Length Failsworth West October Resurface Completed
29 Beech Street Full Length Failsworth West September Resurface  
30 Glen Grove Full Length Royton North July Resurface Completed
31 Alexandra Street Full Length Alexandra September Resurface  
32 Filbert Street Full Length St. James' October Resurface  
33 Chapel Lane Full Length Royton North July Resurface Completed
34 Lewis Street Full Length Crompton August Resurface Completed
35 Woodlands Full Length Failsworth West October Resurface Completed
36 Holmfirth Road Full Length  Saddleworth South August / September Pre Patching  
37 Ashton Road Honeywell Ln, Copster Hill Rd, Hathershaw Ln, Fir Tree Ave Junctions Medlock Vale August / September Resurface  
38 Denton Lane Arne St to Walsh St Chadderton Central July / August Surface Treatment  
39 Ronald Street Full Length Waterhead August Surface Treatment  
40 Queens Road Full Length Alexandra August Surface Treatment  
41 Waverley Street Full Length St. James' August Surface Treatment  
42 Balfour Street Full Length Waterhead August Surface Treatment  
43 Villa Road Full Length Alexandra August Surface Treatment  
44 Eustace Street Broadway to Mill Chadderton North August Surface Treatment  
45 Cranbrook Street Full Length St. Mary's August Surface Treatment  
46 Bartlemore Street Full Length St. James' October Resurface  
47 Age Croft Full Length Alexandra August Surface Treatment  
48 Newport Street Full Length Werneth August SurfaceTreatment  
49 Wellington Road Windsor Rd to Lee St Werneth August Surface Treatment  
50 Scholes Drive Full Length Chadderton South August Surface Treatment  
51 Nugget Street No. 62 to Glodwick Road St. Mary's September Resurface Completed
52 Lydgate Dr / Kestrel Ave Full Length St. Mary's August Surface Treatment  
53 Birch Avenue Full Length Failsworth West August Surface Treatment  
54 Werneth Hall Road Lee St to No.38 Werneth May Resurface Completed
55 Bradshaw St / Old Church St Full Length St. Mary's October Resurface  
56 Cowie Street Full Length Shaw August Surface Treatment  
57 Brompton Street Hardy St to Redford St St. Mary's August Surface Treatment  
58 Whitby Road Full Length Alexandra August Surface Treatment  
59 Bardsley Vale Avenue Full Length Medlock Vale November Resurface  
60 Dove Street Full Length St. Mary's August Resurface  
61 Breeze Hill Road Full Length St. Mary's August Surface Treatment  
62 Falmouth Street Full Length Alexandra November Resurface  
63 Whitehall Street Full Length St. Mary's October Resurface  
64 Wrigley Street Full Length St. Mary's August Surface Treatment  
65 Chelmsford Street Full Length Werneth August Surface Treatment  
66 Saint Hildas Drive Full Length Coldhurst October Resurface  
67 Near Birches Parade Full Length Alexandra August Surface Treatment  
68 Boston Street Full Length Alexandra August Surface Treatment  
69 Hardy Street Park Rd to Waterloo St St. Mary's August Surface Treatment  
70 Cemetery Road Full Length Failsworth East September Resurface Completed
71 Wolverton Avenue Full Length Hollinwood May Resurface Completed
72 Rivington Drive Full Length Shaw July / August Surface Treatment  
73 Flora Street Full Length Coldhurst October Resurface  
74 Bismarck Street Full Length St. Mary's August Surface Treatment  
75 Cornwall Crescent Full Length Saddleworth North July / August Surface Treatment  
76 Salem Grove Full Length St. Mary's August Surface Treatment  
77 Charnwood Close Full Length Crompton July / August Surface Treatment  
78 Kent St / Port St Full Length Medlock Vale October Surface Treatment  
79 Mulmount Close Full Length Hollinwood August Surface Treatment  
80 Waugh Avenue Full Length Failsworth East August SurfaceTreatment  
81 Vulcan Street Junction Stoneleigh Primary St. James' October Resurface  
82 Whitland Drive Full Length Hollinwood August Surface Treatment  
83 Ceylon Street Full Length St. Mary's August Surface Treatment  
84 Osborne Street Full Length Shaw October Surface Treatment  
85 Middleton Road Cinder Hill Ln to Highlands Royton North July Resurface Completed
86 Chadderton Way Burnley Lane to Featherstall Road North Coldhurst August / September Surface Treatment  
87 Cemetery Road Full Length Royton North July Resurface Completed
88 Gorse Avenue Full Length Alexandra July / August Surface Treatment  
89 Phillimore St / Livingstone St Full Length Saddleworth West and Lees July / August Surface Treatment  
90 The Avenue Full Length Crompton July / August Surface Treatment  
91 Peels Avenue Full Length Saddleworth West and Lees July / August Surface Treatment